Frauthy/Project Management

v37 · 2026-07-28

Sequence and readiness

Dependency map

The ribbon is the visual signature; the edge table is the accessible source-equivalent. Hard, sequence, and informational edges are never conflated.
7 dependency edges
FromDepends onKindState
CI meshSEAL-THE-SEAMSinformationalAt risk
Deploy-readySEAL-THE-SEAMShardAt risk
Deploy-readyCI-MESHsequenceAt risk
Observe everywhereSEAL-THE-SEAMSsequenceAt risk
Frauthy protects FrauthySEAL-THE-SEAMShardComplete
Cuitty adopts FrauthySEAL-THE-SEAMShardNot started
TUI & status siteCI-MESHsequenceIn progress

Critical path

  1. Seal the seamsComplete
  2. Deploy-readyAt risk
  3. Frauthy protects FrauthyComplete
  4. Cuitty adopts FrauthyNot started